Rattray foundation Head office
Rattray foundation head office
Our most challenging project yet where we had to build on a gradient and the base was all clay
Obviously rammed earth adds some additional challenges to this type of construction
Embedded in the clay was huge granite rocks that had to be burnt and cooled to break before we could get
Down to foundation level
All foundations in the basement are reinforced 1m x 0.8 with 16 mm rebar
Olso tied to these vertically where tie bars for the retaining wall this had to be done as
three sides of the wall are holding back the clay
The vertical bars that will run up the retaining walls to create a stressed member
Shows the bars that will run all the way through the wall to the top of the slab
Then two lines of bricks 300 mm apart with our Steal in the cavity we can lift three lines at a time and then
Fill with concrete
The following pic shows how the slab beams are being put into place these will hold the
Blocks that will form the base of the concrete
Two things to note the double plastic membrane
And the top of the walls the concrete and the reinforcing to tie into the slab
The same time we where doing that we started the curved foundations for the front walls
The auditing part when the first shutters come off .The wall smells so good when you first take of the shutter it's a moist smell like inside a cave
The coloring was made by washing clay with water and extracting the red pigment
Then using the pigment stained water to make the mixes of sand
Here you can see the process as the shutters are moved up the wall till the wall is complete
The colors will be further intensified by washing the wall with an acid wich removes all
The cement coloring
As we get to the under slab level all the bottom ramming must be completed
Comments
Post a Comment